Florida Department of Environmental Protection Bob Martinez Center 2600 Blair Stone Road Tallahassee, Florida 32399-2400 |
Storage Tanks & Contamination Monitoring Information |
|||||||||
| Journal Report | |||||||||||
| Report Run Date: 04/25/2021 Last Data Refresh: 04/24/2021 Report Generated from DOPPLER | |||||||||||
| Facility ID: | 9101200 | ||||||||||
| Facility Name: | HOBO PANTRY FOOD STORE #4 | ||||||||||
| 09/28/2007 | Enforcement Referral Activity | Bristol, Susan M. | |||||||||
| Activity Result: | Accepted | Activity Status: | Closed | ||||||||
| Activity Closed Date: | 09/28/2007 | ||||||||||
| Events: | |||||||||||
| Event Type: | Activity/Document was accepted on this date | Date: | 09/28/2007 | ||||||||
| Comment: | The Northwest District Storage Tank Section accepts the enforcement referral for the failure to submit a SAR for the January 12, 2004 discovery of contamination. | ||||||||||
| Events: | |||||||||||
| Event Type: | Activity/Document was acknowledged on this date | Date: | 09/28/2007 | ||||||||
| Comment: | The Northwest District Storage Tank Section acknowledges the submittal of the enforcement refrral for the failure to submit a SAR for the January 12, 2004 discovery of contamination. | ||||||||||
| Events: | |||||||||||
| Event Type: | Activity has been submitted for approval | Date: | 09/28/2007 | ||||||||
| Comment: | The Northwest District Storage Tank Section is submitting this enforcement referral to the Northwest District Storage Tank Section. | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 12/10/2007 | User: | BRISTOL_S | ||||||||
| Description: | The Northwest District Storage Tank Section is submitting this enforcement referral to the Northwest District Storage Tank Section for the SAR due to be submitted to the Department on or before April 1, 2008 for the July 5, 2007 discovery of contamination. | ||||||||||
| 09/28/2007 | Enforcement Tracking Activity | Bristol, Susan M. | |||||||||
| Activity Status: | Open | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 12/10/2007 | User: | BRISTOL_S | ||||||||
| Description: | The Northwest District Storage Tank Section acknowledges the submittal of the enforcement referral from the Northwest District Storage Tank Section for the SAR due to be submitted to the Northwest District on or before April 1, 2008 for the July 5, 2007 disocvery of contamination. | ||||||||||
| 04/14/2003 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | TANK COMPLIANCE RE-INSPECTION | Activity Status: | Closed | ||||||||
| Completion Notes: | PIPING: GREEN ENVIRON GEOFLEX DOUBLEWALLED 1.5" DIAMETER | ||||||||||
| 02/10/2003 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | RESPONSE RECEIVED BY DEPARTMENT | Activity Status: | Closed | ||||||||
| 11/22/2002 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | RESPONSE RECEIVED BY DEPARTMENT | Activity Status: | Closed | ||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 640(3)(c)3 | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/06/2016 | User: | GLENN_LE_1 | ||||||||
| Description: | Records: - Current Storage Tank Registration Placard present – (3) tanks; - Financial Responsibility: Ironshore Specialty Insurance Company, coverage period is 12/01/2015 to 12/01/2016; - Certification of Financial Responsibility Form (CFR) – present, complete and accurate; - Written Release Detection Response Level (RDRL) – present, complete and accurate; - Monthly release detection monitoring records reviewed: 01/15/2014 to 03/08/2016; records include: - Electronic monitoring of the tank interstices and visual monitoring of the dispensers/liners, sumps and spill containment buckets (including interstices); - Alarms noted for the Diesel interstice sensor in November 2014 and January 2015. Incident Notification Forms (INF) and investigation results received; - Inspections performed once a month but not greater than 35 days apart. - Annual In-Line Leak Detector tests performed by Scott Drew, Valley Tank Testing, on 02/17/2015 and by Scott Beck, Valley Tank Testing, on 02/16/2016 with passing results; next test due by 02/16/2017. - Annual Operability tests of the Veeder-Root alarm panel and associated electronic sensors in the interstices and the visual gauge in the Diesel spill bucket interstice performed by Scott Drew, Valley Tank Testing, on 02/17/2015 and by Scott Beck, Valley Tank Testing on 02/16/2016 with passing results; next test due by 02/16/2017. - Biennial Breach of Integrity test for all three USTs performed by Steve Foster, Tank Tech, on 11/06/2014 with passing results; next test is due by 11/06/2016. - Operator and Training Certifications - The Class A/B/C Operator training certifications were available for review. Per 40 CFR 280 Subpart J, United States Environmental Protection Agency (USEPA), all UST owners are to have designated and trained operators (Class A, B, & C) by October 13, 2018. Please see the following website (http://www.dep.state.fl.us/waste/categories/tanks/pages/op_train.htm) for further information. Final inspection report e-mailed to Fran Franconi at: ffrancon@circlek.com. | ||||||||||
| 11/12/2002 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | TANK ANNUAL COMPLIANCE INSPECTION | Activity Status: | Closed | ||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 710(2) | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/06/2016 | User: | GLENN_LE_1 | ||||||||
| Description: | Records: - Current Storage Tank Registration Placard present – (4) tanks; - Financial Responsibility: Ironshore Specialty Insurance Company, coverage period is 12/01/2015 to 12/01/2016; - Certification of Financial Responsibility Form (CFR) – present, complete and accurate; - Written Release Detection Response Level (RDRL) – present, complete and accurate; - Monthly release detection monitoring records reviewed: 01/15/2014 to 03/08/2016; records include: - Electronic monitoring of the tank interstices and visual monitoring of the dispensers/liners, sumps and spill containment buckets (including interstices); - No issues noted; inspections performed once a month but not greater than 35 days apart. - Annual In-Line Leak Detector tests performed by Scott Beck, Valley Tank Testing, on 11/20/2014 and 11/18/2015 with passing results; next test due by 11/18/2016. - Annual Operability tests of the Veeder-Root alarm panel and associated electronic sensors in the interstices performed by Scott Beck, Valley Tank Testing, on 11/20/2014 and 11/18/2015 with passing results; next test due by 11/18/2016. - Biennial Breach of Integrity tests for the three in service USTs performed by Tank Tech, on 3/05/2016 with passing results. However the Interstice probes in the Premium and Diesel tanks failed. Interstice probes must be replaced or repaired and re-tested immediately and the results sent to the Department. - Operator and Training Certifications - The Class A/B/C Operator training certifications were available for review. Per 40 CFR 280 Subpart J, United States Environmental Protection Agency (USEPA), all UST owners are to have designated and trained operators (Class A, B, & C) by October 13, 2018. Please see the following website (http://www.dep.state.fl.us/waste/categories/tanks/pages/op_train.htm) for further information. Final inspection report e-mailed to Fran Franconi at: ffrancon@circlek.com. | ||||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 700(1)(c)1 | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/06/2016 | User: | GLENN_LE_1 | ||||||||
| Description: | Release Detection: - Tanks: Electronic monitoring of tank interstices; - Piping: Visual monitoring of piping interstice with electronic monitoring secondary per the facility Release Detection Response Level statement (RDRL); - Visual inspections of dispensers/liners and spill containment buckets (including interstices); - Veeder-Root Simplicity panel checked – T3 Delivery Needed; - Test button pushed – visual and audible alarms functional; - Tank interstitial alarm history on file; not all alarms correspond to testing records received. - Alarm history report shows March 8, 2016 Premium & Diesel alarms. Testing records must be received or an Incident Notification Form (INF) and investigation results submitted to the Department. Note: (1) 10,000-gallon tank was placed out of service on June 1, 2011. Corresponding STP has been removed and all piping capped. AST may remain out of service for up to ten years (June 1, 2021) at which time the tank must either be placed back into service or be permanently closed. Tanks/Sumps/Piping: (3) 10,000-gallon, and (1) 6,000-gallon Phoenix System Parabeam, double-walled, (fiberglass inner wall, steel outer wall) tanks. Underground piping is Ameron Dualoy 3000/LCX, double-walled, fiberglass piping. Tanks are equipped with: - (4) Western Fiberglass, single-walled, fiberglass STP sumps; - All sumps appeared to have a minor amount of Petroleum Contact Water (PCW); recommend removing PCW. - All sumps appeared to be intact; - (3) FE Petro STPs with mechanical leak detectors; - Secondary piping appears open to sumps; - Electronic sensors present and positioned correctly; per the facility RDRL, the sensors are not the primary form of release detection and therefore are considered secondary. - (4) Double-walled, Emco-Wheaton spill containment buckets; - Interstices monitored by manually removing dip sticks; - Diesel checked – dry; - Out of service checked – dry; - Regular and Premium – access not provided to the spill containment bucket interstices for inspection; - Access must be provided to the Regular and Premium spill bucket interstices and the Department contacted for re-inspection. - PCW was present in all of the primary spill containment buckets; PCW must be removed and the Department contacted for re-inspection. - (4) Tight fills; out of service fill is capped. - (4) Fill covers marked per API RP 1637; out of service cover has been painted black; - Overfill protection – overfill prevention valves present in the drop tubes; - (2) Dual point vapor recovery present for gasoline products (not currently required for diesel); - Poppet valves present and appear to be operational; - Vapor recovery covers marked per API RP 1637; - (4) Vent lines with caps present; Dispensers: - (3) Gilbarco Veeder-Root dispensers checked; - Western Fiberglass dispenser liners; - All liners appeared clean, dry and intact; - Shear valves have anchors; - Secondary piping appears open to the liners; - Nozzles/breakaways/hoses checked and appeared to be in good condition; - Dispenser #1/2 appears to have broken penetration boots. Broken boots must be replaced and the Department contacted for re-inspection. | ||||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 700(1)(a)1 | ||||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 600(1)(k) | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/06/2016 | User: | GLENN_LE_1 | ||||||||
| Description: | Release Detection: - Tanks: Electronic monitoring of tank interstices; - Piping: Visual monitoring of piping interstice with electronic monitoring secondary per the facility Release Detection Response Level statement (RDRL); - Visual inspections of dispensers/liners and spill containment buckets (including interstices); - Veeder-Root TLS-350 panel checked – L2 & L4 Fuel Alarms (Regular and Premium STP sumps); - Test button pushed – visual and audible alarms functional; - Tank interstitial alarm history report on file; all electronic sensor alarms correspond to the most recent testing. Tanks/Sumps/Piping: (3) 9,816-gallon, Primary Containment System, double-walled, fiberglass tanks. Underground piping is A.O. Smith, double-walled, fiberglass piping. Tanks are equipped with: - (3) Fiberglass, single-walled, STP sumps; - All sumps have Petroleum Contact Water (PCW) at or above the piping (see photos); - PCW must be removed, disposed of properly and the Department contacted for re-inspection. - (3) FE Petro STPs with mechanical leak detectors; - Electronic sensors present and positioned correctly; per the facility RDRL, the sensors are not the primary form of release detection and therefore are considered secondary. - (3) Double-walled, Emco-Wheaton spill containment buckets; - Interstitial visual gauge for Diesel indicated the interstice was dry at the time of inspection; - Interstices monitored by manually removing dip sticks for Premium and Regular; - No access to the Premium interstice; access must be provided and the Department contacted for re-inspection. - Fuel noted in the interstice of the Regular spill bucket. An Incident Notification Form must be submitted to the Department, and an investigation performed to determine the cause of the product intrusion with the investigation results submitted to the Department. - PCW was present in all of the primary spill containment buckets; however PCW was removed while on site. - (3) Tight fills; - (3) Fill covers marked per API RP 1637; - Overfill protection – overfill prevention valves present in the drop tubes; - (2) Dual point vapor recovery present for gasoline products (not currently required for diesel); - Poppet valves present and appear to be operational; - Vapor recovery covers marked per API RP 1637; - (2) Vent lines with caps present; Dispensers: - (2) Gilbarco Veeder-Root dispensers checked; - Fiberglass dispenser liners; - All liners appeared clean, dry and intact; - Shear valves have anchors; - Secondary piping appears open to the liners; - Nozzles/breakaways/hoses checked and appeared to be in good condition; | ||||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | SNC-B | Status: | Closed | ||||||||
| Rule: | 600(1)(d) | ||||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | SNC-B | Status: | Closed | ||||||||
| Rule: | 400(3) | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/06/2016 | User: | GLENN_LE_1 | ||||||||
| Description: | Records: - Current Storage Tank Registration Placard present – (4) tanks; - Financial Responsibility: Ironshore Specialty Insurance Company, coverage period is 12/01/2015 to 12/01/2016; - Certification of Financial Responsibility Form (CFR) – present, complete and accurate; - Written Release Detection Response Level (RDRL) – present, complete and accurate; - Monthly release detection monitoring records reviewed: 01/15/2014 to 03/08/2016; records include: - Electronic monitoring of the tank interstices and visual monitoring of the dispensers/liners, sumps and spill containment buckets (including interstices); - Multiple alarms noted throughout 2014 and 2015. INFs and investigation results received; - Inspections performed once a month but not greater than 35 days apart. - Annual In-Line Leak Detector tests performed by Scott Beck, Valley Tank Testing, on 01/09/2014, 12/15/2014 and 12/09/2015 with passing results; next test due by 12/09/2016. - Annual Operability tests of the Veeder-Root alarm panel and associated electronic sensors in the interstices was performed by Scott Beck, Valley Tank Testing, on 01/09/2014, 12/15/2014 and 12/09/2015 with passing results; next test due by 12/09/2016. - The following Operability test of the electronic sensors in the interstices were performed due to sensor alarm issues. Premium Sensor test performed by Scott Beck, Valley Tank Testing on 07/18/2014 with passing results and Regular Sensor test on 11/05/2015 with passing results. - Annual Operability tests of the visual gauges in the Premium and Diesel spill bucket interstices was performed by Scott Beck, Valley Tank Testing, on 01/09/2014, 12/15/2014 with passing results and on 12/09/2015 with failing results. New Premium and Diesel Spill Buckets installed and test performed by Cristobal Alvarenga, Valley Tank Testing, on 12/23/2015 with passing results; next test due 12/23/2016. - Breach of Integrity test for all four USTs performed on 10/28/2011 with passing results; next test is due by 10/28/2016. - Operator and Training Certifications - The Class A/B/C Operator training certifications were available for review. Per 40 CFR 280 Subpart J, United States Environmental Protection Agency (USEPA), all UST owners are to have designated and trained operators (Class A, B, & C) by October 13, 2018. Please see the following website (http://www.dep.state.fl.us/waste/categories/tanks/pages/op_train.htm) for further information. Final inspection report e-mailed to Fran Franconi at: ffrancon@circlek.com. | ||||||||||
| 11/12/2002 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 400(2)(a)6 | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/06/2016 | User: | GLENN_LE_1 | ||||||||
| Description: | Release Detection: - Tanks: Electronic monitoring of tank interstices; - Piping: Visual monitoring of piping interstice with electronic monitoring secondary per the facility Release Detection Response Level statement (RDRL); - Visual inspections of dispensers/liners and spill containment buckets (including interstices); - Veeder-Root TLS-350 panel checked – L14 Fuel Alarm (Regular 2 STP North Tank); - Test button pushed – visual and audible alarms functional; - Tank interstitial alarm history report on file; all electronic sensor alarms correspond to the most recent testing, except L2 (Regular 1 Interstice) which has a February 10, 2016 alarm. Incident Notification Form (INF) has been received by the Department and an investigation will be performed. Tanks/Sumps/Piping: (2) 10,000-gallon and (1) 15,000-gallon Xerxes, double-walled, fiberglass tanks, and (1) 5,000-gallon, Metal Products Elutron Plasteel jacketed, double-walled steel tank. Underground piping is Petro Technik, double-walled, flex piping. Tanks are equipped with: - (4) Fiberglass, single-walled, STP sumps and (1) piping sump; - Regular #1 sump has Petroleum Contact Water (PCW) above the piping (see photo); - PCW must be removed, disposed of properly and the Department contacted for re-inspection. - Access tot he Regular #2 STP sump not provided at time of inspection; - Access must be provided and the Department contacted for re-inspection. - All other sumps appear to be clean, dry and intact; - (4) FE Petro STPs with mechanical leak detectors; - Premium STP is showing heavy corrosion (see photo) and must be sanded, painted and the Department contacted re-inspection. - Electronic sensors present and positioned correctly; per the facility RDRL, the sensors are not the primary form of release detection and therefore are considered secondary. - (4) Double-walled, Emco-Wheaton spill containment buckets; - PCW was present in all primary spill containment buckets; however PCW was removed while on site. - Interstitial visual gauges for Premium and Diesel indicated the interstice was dry at the time of inspection; - Interstices monitored by manually removing dip sticks for the two Regular spill buckets; - Minor condensation noted within Regular #2 interstice at time of inspection. - PCW noted in the interstice of Regular #1 spill bucket. An Incident notification Form must be submitted to the Department, and an investigation performed to determine the cause of the product intrusion with the investigation results submitted to the Department. - All spill buckets appeared intact; - (4) Tight fills; - (4) Fill covers marked per API RP 1637; - Overfill protection – overfill prevention valves present in the drop tubes; - (3) Dual point vapor recovery present for gasoline products (not currently required for diesel); - Poppet valves present and appear to be operational; - Vapor recovery covers marked per API RP 1637; - (4) Vent lines with caps present; Dispensers: - (10) Dispensers checked; - Polyethylene dispenser liners; - All liners appeared clean, dry and intact; with the exception of dispenser #7/8. PCW was noted within the liner below the piping; recommend removing PCW. - Minor seepage noted at piping joint above the shear valve (see photos) at dispensers #3/4, #11/12, #13, #14 and #15. Leaks must be repaired and the Department contacted for re-inspection. - Shear valves have anchors; loose bolt noted within dispenser #14. Bolt must be tightened. - Secondary piping appears open to the liners; - Nozzles/breakaways/hoses checked and appeared to be in good condition; | ||||||||||
| 04/19/2002 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | RESPONSE RECEIVED BY DEPARTMENT | Activity Status: | Closed | ||||||||
| 11/28/2001 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 450(2)(a) | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 06/02/2014 | User: | MORRISON_CY_1 | ||||||||
| Description: | AST Advanced Maunufacturing and Power Systems (EQ-636) | ||||||||||
| 11/28/2001 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | TANK ANNUAL COMPLIANCE INSPECTION | Activity Status: | Closed | ||||||||
| 11/28/2001 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 820(1)(a),(b),(c) | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 06/02/2014 | User: | HATCHER_JD_1 | ||||||||
| Description: | AST Performed inspect on: 6/02/2014 Placard: 2013/2014 not provided. Fees not paid FR: ok CFR: ok RDRL: ok Monthlys: Provided and current. Annual Operability: Ok Overfill: Manual stick. Tank 1. ok Anti-siphon: In place Containment Area: n/a Spill Buckets: ok Dispensers/Hoses: n/a Leak Detection: monthly visuals of ast and above groumd piping. Electronic rupture basin semsor | ||||||||||
| 02/06/2001 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | TANK COMPLIANCE RE-INSPECTION | Activity Status: | Closed | ||||||||
| 12/27/2000 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | RESPONSE RECEIVED BY DEPARTMENT | Activity Status: | Closed | ||||||||
| 11/28/2000 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 700(1)(a)1 | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/30/2012 | User: | NEWBERG_DR_1 | ||||||||
| Description: | Non-compliance letter mailed to owner representative. | ||||||||||
| 11/28/2000 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | TANK ANNUAL COMPLIANCE INSPECTION | Activity Status: | Closed | ||||||||
| 11/28/2000 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | Minor | Status: | Closed | ||||||||
| Rule: | 700(1)(b)2a | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 04/30/2012 | User: | VOGT_CL_1 | ||||||||
| Description: | The Veeder Root was operational without alarms. The PUL sump had liquid which from the previous rain event. This sump recieves a large storm water flow from the street and often is under water. This was an error created during the final grading of the parking lot. It was recommended that some form of barrier be installed or cutting out the sump cover and raising the sump lid above the existing grade so as to prevent storm water from directly impacting this sump. The facility constantly removes storm water from this sump despite the sump lid being secure. | ||||||||||
| 10/31/2000 | Comment | MIGRATION | |||||||||
| Description: | COMPLIANCE: UST CLOSURE | ||||||||||
| 12/28/1999 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | RESPONSE RECEIVED BY DEPARTMENT | Activity Status: | Closed | ||||||||
| 12/01/1999 | Violation Closed | Godwin, Christine | |||||||||
| Significance: | SNC-B | Status: | Closed | ||||||||
| Rule: | 400(3) | ||||||||||
| Comments: | |||||||||||
| Comment Date: | 11/18/2010 | User: | ZIMMERMAN_CA_1 | ||||||||
| Description: | Leak was repaired to primary line and line test was conducted and passed. Repairs to line were conducted by JMP Solution. Local program was not notified when repairs we being made. Facility will be written up for Failure to Notify when re-inspection is conducted. Copy of of all repair documentation will also be attracted to re-inspection. | ||||||||||
| 12/01/1999 | Legacy Activity | Godwin, Christine | |||||||||
| Activity Name: | TANK ANNUAL COMPLIANCE INSPECTION | Activity Status: | Closed | ||||||||